Current Construction Projects

Phase I, Intelligent Transportation System 2nd Street/Edmond Road Corridor Project
This project consists of installing fiber optic cable and replacing the traffic signal cabinets and controllers and associated signal equipment at 21 intersections from Santa Fe Avenue, east to Saints Boulevard in order to bring them into compliance with the National Transportation Communication for Intelligent Transportation System Protocol (NTCIP) standards. The project will also include installation of wireless radios at four of the city water towers. These intersections will connect to the Traffic Management Center via fiber optics and wireless communication network.

The Oklahoma Department of Transportation awarded this project on April 7, 2014 to Midstate Traffic Control, Inc in the amount of $3,041.862.75. 

October 2016 Update:  Contractor is working on final "punch list" of items that will need to be addressed before the City will accept the project from the contractor.  Unknown completion date.   

33rd and Broadway
This project will provide for dual southbound and westbound left turn lanes, a single eastbound, westbound and southbound right turn lane. The entire intersection will be reconstructed in concrete pavement. Signal light modifications will accommodate the changes in lane configurations. This project is part of the 2000 Sales Tax Improvements. 

Oklahoma Department of Transportation has awarded this project to Allen Contracting Inc. in the amount of $5,144,114. Work will begin on July 20, 2015. The contract time is 330 calendar days. Contractor is to maintain 2 through lanes on Broadway along with a single left turn lanes at all times during construction. 33rd street will have one through lane along with one left turn lane at all times. Motorists are encouraged to use alternate routes during construction

October 2016 Update:  Contractor will be installing some hand rail at several locations on 33rd Street. Once this work is finished the project will be complete. 

Covell and Santa Fe
Covell and Bryant
Short term improvements include construction of left turn lanes and left turn signal phasing. The project is funded with 100% City funds estimated at $1,500,000. Construction plans are 95% complete. The anticipated start date is late summer/winter of 2016.

October 2016 Update: There are 2 remaining parcels of land that need to be secured at the Bryant location. Utility companies have been authorized to start relocating their lines, which should be complete by December.

Covell Widening, Fairfax to I-35 Southbound on/off ramp
This project will widen Covell to a four-lane divided roadway. There will be a section of widening east of Sooner six lanes wide to accommodate future commercial development. There will be left and right turn lanes at major commercial driveways. The project also includes widening the intersection of Covell and Sooner and will include a signal light as well as street lighting throughout the project along with 10 foot wide multi-use paths on both sides of the street.

Oklahoma Department of Transportation has awarded this project to Allen Contracting Inc. in the amount of $11,798,388. Work began on July 20, 2015. The contract time is 310 calendar days. Contractor is to maintain 1 through lane on Covell and on Sooner at all times during construction.  Motorists are encouraged to use alternate routes during construction

October 2016 update: Contractor continues with installation of storm structures and retaining wall and modifying sub-grade. Contractor is ahead of schedule.




Engineering Department
Steve Manek
Director of Engineering

10 S. Littler Ave.
Edmond, OK 73034
View Map

Ph: (405) 359-4770
Fax: (405) 359-4696

Hours
Monday - Friday
8:00 am - 5:00 pm
Help Center