Water Production Report
Water Treatment Plant and Wells
Water Production for 2007
- Water wells – 1,958,751,054 gallons
- Treatment plant (water treated from Arcadia Lake) – 1,550,673,219
- Total annual production (both plant and wells) – 3,509,673,219 gallons
Peak Demand – 19,948,012 gallons on August 15, 2007
During 2005, a pipeline from Oklahoma City’s water distribution
system was placed in service to Edmond’s 33rd Street storage and
pumping site. Total volume of water purchased from Oklahoma City in
2007 was 4,126,000 gallons.
Recently Completed Projects to Enhance Water Production and Supply
- Booster Stations – for maintaining good water pressure in the distribution system
- Improvement in the water transmission and distribution lines – to deliver water more effectively
- Design and Construction of the Northwest Complex – for water storage and distribution